When submitting an Application for Payment, it is acceptable to bill for unapproved change-order work as long as it appears on a separate line from the original-contract items.
0
1
Tags
Electrical Contracting Business Operations
Running an Electrical Contracting Business Course
Related
Keeping Field and Office in Sync on Progress Billing
When submitting an Application for Payment, it is acceptable to bill for unapproved change-order work as long as it appears on a separate line from the original-contract items.
You are an electrical contractor preparing your monthly Application for Payment. You recently finished an approved change order to install additional exterior lighting that was not in the original contract. How should you incorporate this change order into the payment application?
As an electrical contractor preparing your monthly Application for Payment, match each project scenario with how it should be handled on the pay application.
A general contractor requests additional data drops midway through your electrical project. By analyzing the financial risks and auditing requirements, arrange the steps you must take to properly manage and bill for this change order on your Application for Payment.
A general contractor is evaluating an electrical subcontractor's draft Application for Payment and decides to return it for revision. The GC justifies this decision because the subcontractor combined an approved extra work ticket into the main base-scope line item, violating the critical requirement that change-order work must always appear on ________ lines to allow auditors to properly trace the changed scope.
You are designing the billing framework for a new commercial electrical project. To ensure your payment applications are auditable and to prevent disputes regarding base-scope progress, arrange these components in the correct order to construct a professional line-item breakdown.
You are preparing your monthly Application for Payment for a commercial project. You have completed $12,000 of the original contract work. You have also finished $2,000 of work for 'Change Order #1' (signed and approved) and $1,500 of work for 'Change Order #2' (requested by the owner but not yet signed). Which of the following line-item configurations is the correct way to present this to ensure your payment application is not rejected?
You are designing the logic for your electrical business's new automated billing system. To ensure that every Application for Payment generated by the software is audit-ready and protected against rejection, arrange the steps the system must take to properly handle change orders.
Why is it considered a best practice for an electrical contractor to list approved change orders on separate lines of a payment application rather than simply increasing the dollar value of the original contract line items?
A general contractor’s auditor flags an electrical subcontractor’s payment application for 'inflated progress' because the 'Branch Wiring' line item is reported at 110% completion. The subcontractor explains that the extra 10% is for an approved change order that was added to the original line item. Analyzing the auditor's perspective, why did this billing structure lead to a dispute?