Multiple Choice

You are preparing your monthly Application for Payment for a commercial project. You have completed $12,000 of the original contract work. You have also finished $2,000 of work for 'Change Order #1' (signed and approved) and $1,500 of work for 'Change Order #2' (requested by the owner but not yet signed). Which of the following line-item configurations is the correct way to present this to ensure your payment application is not rejected?