Sequence Ordering

An electrical contractor is managing the material procurement for a commercial retail renovation. The project requires custom electrical panels with a 12-week lead time, standard conduit and wire, and expensive architectural light fixtures that will be installed during the final week. Arrange the steps of the material procurement, staging, and inventory process in the correct sequence to ensure smooth operations, minimize carrying costs, and prevent on-site theft.