True/False

An electrical contractor who is experiencing both severe cash-flow shortages and project delays due to missing materials decides to implement a new procurement policy: the company will order all project materials—including both high-use commodity items (such as standard wire and boxes) and highly specialized equipment (such as custom panels and switchgear)—exactly two weeks before their scheduled installation date.

This policy is a logically sound operational strategy that will successfully resolve both cash-flow shortages and project delays simultaneously.