An electrical contractor is mid-project when a design flaw is discovered that requires additional wiring. The owner and contractor agree that the work is within the project's general scope and they agree on the additional $1,500 cost, but they cannot agree on whether the work requires a two-day or three-day schedule extension. The owner issues an AIA-style Construction Change Directive (CCD) to ensure the work begins immediately. Evaluate the appropriateness of using a CCD in this specific scenario.