Multiple Choice

You are an electrical contractor wiring a new office suite when the project owner decides to add several emergency backup lights in the main hallway. This change is within the project's general scope, but you and the owner cannot agree on the final labor cost for the installation. To keep the project on track, the owner issues a written AIA-style Construction Change Directive (CCD). How should you respond?