As an electrical contractor, you must evaluate project modification requests and determine the correct administrative action. Match each specific scenario with the appropriate document or classification.
0
1
Tags
Electrician Business Operations
Running an Electrical Contracting Business Course
Related
A construction change directive is a written order used to direct a contractor to proceed with a change in work even when all parties have not yet fully agreed on the terms of the change order.
As an electrical contractor, you are asked by the project owner to add several recessed lights to a conference room. Both parties agree this is a necessary change, but you cannot agree on the final price adjustment yet. Why would the owner issue an AIA-style Construction Change Directive (CCD) in this scenario rather than a standard Change Order?
You are wiring a retail store when the owner urgently asks you to add dedicated circuits for three new display cases. This change is within the general scope of the project. You both agree the work must happen immediately to stay on schedule, but you have not yet reached an agreement on the final price adjustment. To officially direct you to proceed with the work before the final terms are agreed upon, the owner should issue a(n) ____.
Analyze the administrative workflow for managing an urgent project modification using a Construction Change Directive. Arrange the following events in the correct logical sequence to demonstrate how an electrical contractor should handle a change when final terms cannot be immediately agreed upon.
As an electrical contractor, you must evaluate project modification requests and determine the correct administrative action. Match each specific scenario with the appropriate document or classification.
You are developing a written standard operating procedure (SOP) for your new electrical contracting company that addresses how your team should respond when a project owner requests additional work mid-project. The change is clearly within the general scope of the original contract, but you and the owner have agreed on the added time impact while still disagreeing on the final price adjustment. Which of the following SOPs would best protect your company while keeping the project moving forward?