Multiple Choice

You are developing a written standard operating procedure (SOP) for your new electrical contracting company that addresses how your team should respond when a project owner requests additional work mid-project. The change is clearly within the general scope of the original contract, but you and the owner have agreed on the added time impact while still disagreeing on the final price adjustment. Which of the following SOPs would best protect your company while keeping the project moving forward?