Fill in the Blank

You are wiring a retail store when the owner urgently asks you to add dedicated circuits for three new display cases. This change is within the general scope of the project. You both agree the work must happen immediately to stay on schedule, but you have not yet reached an agreement on the final price adjustment. To officially direct you to proceed with the work before the final terms are agreed upon, the owner should issue a(n) ____.