Multiple Choice

An electrical contractor is preparing the billing schedule (Schedule of Values) for a new $100,000 warehouse renovation. To avoid the initial 'dip' in cash flow shown in the provided infographic, which strategy should the contractor apply when assigning values to early project tasks like 'Mobilization' and 'Project Setup'?