Pricing Deposits to Real Mobilization Costs

To price a deposit correctly, calculate the actual costs incurred before the first progress milestone: permit fees, initial material orders, equipment rental or staging, and crew mobilization expenses. Request that total as the deposit rather than defaulting to a round percentage. Include a mobilization line item in the Schedule of Values so the deposit amount is billable in Month 1 before significant physical work is complete. This ensures the contractor's cash position is neutral or positive at project start.