Multiple Choice

You are bidding on a restaurant renovation. The Electrical Plans (E-1) show standard lighting and outlets for the dining area. However, the Kitchen Equipment Schedule (K-1) lists a walk-in freezer and a triple-vat fryer requiring 3-phase power, neither of which appear on E-1. Additionally, the General Contractor’s notes state that the electrician must provide 'conduit only' for the fire alarm system, while a separate fire alarm vendor handles all wiring and devices. Which of the following drafted 'Scope of Work' statements most effectively synthesizes these conflicting documents into a professional and protective project boundary for your bid?