Multiple Choice

You are managing an electrical project where the contract allows your retainage to drop from 10% to 5% once you reach 50% completion. Your billing coordinator suggests skipping the formal request for this reduction, stating: 'The project is moving fast, and it’s better not to bother the General Contractor with extra paperwork for a small percentage change.' Based on the cash flow principles shown in the 'Construction Cash Flow' infographic, evaluate the validity of this suggestion.