Multiple Choice

Your electrical firm is currently at 65% completion on a commercial project. You discover that your team never requested the retainage reduction (from 10% down to 5%) that was contractually available once the project passed 50% completion. Your Project Manager suggests skipping the request now, claiming: 'We already missed the 50% trigger window, so we might as well just wait for the final payout at the end of the job.' Referring to the cash flow challenges shown in the infographic, evaluate this suggestion.