A new electrical contractor is reviewing two recent projects that were similar in scope. On Project A, the contractor ordered all materials a week before the start date, stored them in an unlocked trailer on-site, and had the crew pull what they needed each morning without any tracking. On Project B, a different contractor staggered material deliveries to match the installation schedule, secured materials in a locked storage area, and required the crew lead to sign out materials daily against a