True/False

An electrical contractor is analyzing a project where the budget allocates $50,000 for field labor and $50,000 for custom switchgear. If the contractor claims that both cost categories can be monitored on the exact same weekly timeline because they represent equal direct cost weights, their analysis is incorrect because labor is immediately consumed as it is performed, whereas materials introduce operational risk across a multi-step physical lifecycle (ordering, receiving, staging, and tracking) long before installation begins.