Multiple Choice

An electrical contractor is reviewing the project costs for two different jobs. On Job 1, the labor expenses were over budget because the crew worked slower than the estimated time to install the conduit. On Job 2, the material expenses were over budget because a shipment of conduit was stolen from the job site two days after it was delivered but before it could be installed.

Which analysis best explains why managing the costs on Job 2 represents a more complex operational challenge than managing the costs on Job 1?