Multiple Choice

An electrical contractor reaches 'Substantial Completion' on a commercial warehouse project on January 1st, and the owner begins operating out of the space that day. However, due to administrative delays, the final 'as-built' drawings are not delivered and the final payment is not received until March 1st. On February 1st of the following year, a major lighting contactor fails. The contractor refuses to repair it for free, arguing that the one-year warranty period expired on January 1st. Evaluate the contractor's position based on standard project closeout principles.